ST: 4.2. Calculate the estimated standard deviation

Revision Date: 2005-09-06

The next stage is to calculate the position of the tails of the distribution that has just been drawn. However, in order to calculate the position of the tails, the standard deviation is required. In this version of capability analysis where data has been collected over a period of time, an estimated standard deviation is used. The symbol for the estimated standard deviation is  (read “sigma hat”). The formula for the estimated standard deviation is:

 

 is calculated when constructing a control chart. Substitute M for  if an X-MR chart has been completed. In the example, is 4.653. The denominator (d2) is a weighting factor whose value is based on the subgroup size, n, from the control chart. The value for d2 in the example, based on a subgroup size of 5, is 2.326. A short listing of the d2 values for other subgroup sizes follows. The full table of values is given in the appendix.

  

n 2 3 4 5 6 7 8 9 10
d2  1.128 1.693 2.059 2.326 2.534 2.704 2.847  2.970  3.078
 

The estimated standard deviation for the example is:


The estimated standard deviation is calculated to one more decimal place than the original data.

Previous    Next

 


 The above article is an excerpt of the "Capability Analysis" section of Practical Tools for Continuous Improvement Volume 1 Statistical Tools.

Would you like to...

Print this page Print this page

Email this page Email this page

Post a comment Post a comment

Subscribe me

Add to favorites Add to favorites

Remove Highlighting Remove Highlighting

Edit this Article

Quick Edit

Export to PDF

User Opinions (2 votes)

100% thumbs up 0% thumbs down

How would you rate this answer?



Thank you for rating this answer.

Related Articles

No related articles were found.

Attachments

No attachments were found.

Continue